When ordering a customized Double-end Saw, buyers should use the normal 20-35-day delivery period as an initial planning reference. However, the available product information does not identify a fixed number of additional days for customization. The final lead time must be confirmed in writing after the technical requirements and production plan have been reviewed.
A single customized Double-end Saw can be ordered because the minimum order quantity is 1 set. Even so, the delivery schedule depends on the extent of the requested modifications, the need for engineering confirmation, manufacturing arrangements, machine testing, packaging, and transportation.
The supplied business information lists the Double-End Saw Series as one of the company’s principal product categories, but it does not publish a product-specific extension for customization. A delivery figure provided for a Manual Edge Bander is not applicable to a customized Double-end Saw and should not be used as a substitute.
The manufacturer and buyer should first define the machine configuration and all requested changes. These may include processing functions, dimensions, electrical requirements, tooling, control systems, line integration, and other non-standard specifications. Once these details are confirmed, the factory can establish the engineering sequence and provide a more reliable delivery date.
Production planning for a customized machine may include sheet metal fabrication, frame welding, component installation, assembly, and final debugging. During these stages, the company states that it checks dimensional tolerance, fitting clearance, transmission coaxiality, and electrical compatibility.
Testing also needs to be included in the agreed schedule. Before dispatch, the equipment is subjected to no-load operation, extended full-load running, precision remeasurement, noise and vibration checks, and electrical stability testing. A pre-shipment inspection then confirms the machine quantity, spare parts, consumables, tools, appearance, packaging, and documentation.
Double-end sizing and precision cutting are important in wood door and wooden window manufacturing. Depending on the production process, a complete solution may also involve profile milling, lock-hole drilling, hinge-slot processing, contour shaping, and fine sanding. Defining the required workflow in advance helps the manufacturer evaluate the technical scope and prepare an accurate schedule.
Sun Hunt has provided complete production line planning for woodworking customers in India and the UAE. Documented projects include a 19-machine wooden door factory line and a 10-machine wood-processing line. Customer feedback highlights stable operation, professional planning, and responsive after-sales service.
| Planning item | Information currently available | What the buyer should do |
|---|---|---|
| Normal delivery period | Typically 20-35 days | Use this as the starting reference for planning |
| Extra customization time | No fixed number of additional days is stated | Obtain a machine-specific timeline after technical review |
| Order quantity | Minimum order quantity is 1 set | A single customized machine may be ordered |
| Testing and inspection | Operational testing and pre-shipment inspection are included in the stated process | Make sure these activities are reflected in the delivery plan |
| Supply capability | Non-standard equipment and complete line solutions are supported | Request a customized quotation for either an individual machine or a full line |
No standard additional period has been published. The 20-35-day window is a normal delivery reference, while the customization extension must be calculated according to the confirmed technical scope.
Yes. The stated minimum order quantity is 1 set, so a single-machine order is supported.
Ask the supplier to confirm the machine configuration, customization requirements, engineering review, manufacturing sequence, testing procedures, packaging, and shipping arrangements. The final delivery commitment should appear in the written quotation or order confirmation.
For planning purposes, begin with the standard 20-35-day delivery reference, but do not regard it as a guaranteed lead time for a customized Double-end Saw. Because no fixed customization allowance is provided, the safest approach is to request a written schedule that separates technical confirmation, production, testing, pre-shipment inspection, and transportation. Foshan Sun Hunt accepts non-standard customized products and complete production line projects, with a minimum order of 1 set. For technical consultation or project support, contact vincent@fsshmachine.cn.
Foshan Sun Hunt Woodworking Machinery Co.,Ltd. develops and manufactures woodworking equipment, including CNC Router Machines, Double-End Saw Series, Planer Machines, Drilling Machines, Edge Banding Machines, and Panel Saws. Founded in 2014, the company operates from a 2,000-square-meter facility in Foshan and maintains management and R&D resources dedicated to woodworking machinery technology. Its documented experience includes wood door and wood-processing production line planning for customers in India and the UAE.

REPORT