An injection mould delivery estimate is meaningful only when the supplier states what event marks its completion. “Delivery” might refer to a finished tool ready for testing, a mould that has completed its first trial, samples awaiting customer sign-off, or the mould’s shipment. These milestones are not interchangeable, so ask the supplier to identify the exact endpoint before agreeing to a schedule.
For the Custom Plastic Injection Mold for Electronic Housing, the listed delivery time is 20–35 days. The product information also mentions mould trial testing, dimensional inspection, and a full check before shipment. However, it does not explicitly say that customer approval of the final samples falls within those 20–35 days. Get that point confirmed in writing.

Supplier schedules often divide mould making from sample approval and subsequent production. For example, one service model gives a 25–35 working-day mould schedule and specifies sample sign-off before shipment. A simple mould may take 20–25 working days, with first article inspection, full dimensional measurement, and a mould running test. Complex precision tooling is quoted at 35–45 working days and may require trial runs over multiple cycles.
When mould development is followed by plastic injection mass production, the stated schedule is 25–35 days for the mould, then another 7–15 days for production after sample approval. This makes approval a distinct milestone. Confirm whether the same separation applies to your project, and whether the production clock starts only after your written sign-off.

Tool specifications can influence trial outcomes, sample changes, and approval timing. Confirm the required mould steel, such as P20, 718H, or 1.2738; compatibility with ABS, PC, or PP; and the requested precision, listed as ±0.02mm. Also agree on single- or multi-cavity design, polishing, texture or matte finish, and expected mould life, which may range from 50,000 to 800,000 shots.
These requirements should be settled early. A change in material, surface finish, cavity layout, or dimensional criteria after tooling begins may call for revisions and additional trials, potentially moving the final approval or shipment date.
| Schedule Description | Activities Listed | Clarify Before Proceeding |
|---|---|---|
| Product delivery: 20–35 days | Mould trial, dimensional inspection, and a full check before shipment. | Does the period end after inspection, sample approval, or shipment? |
| Simple mould: 20–25 working days | First article inspection, full measurement, and mould running test. | Is customer approval included, and how are revisions handled? |
| Standard mould: 25–35 working days | 3D inspection, dimensional checks, mould trial, and sample confirmation. | Does confirmation mean internal validation or written customer sign-off? |
| Complex precision mould: 35–45 working days | CMM testing, surface inspection, and multi-cycle trials. | How many cycles and what approval criteria apply before shipment? |
| Mould plus mass production | 25–35 days for the mould; 7–15 production days after sample approval. | When is approval recorded, and does production start only afterward? |
Longterm Mold holds ISO 9001:2015 certification for the design, manufacture, and sale of precision moulds, as well as the sale of plastic products. Its recorded projects include electronic housing moulds for an Italian manufacturer, a double-shot overmoulding tool for a French product brand, a home appliance mould for a US distributor, and an industrial plastic part mould for an Australian customer. Reported project feedback highlights dimensional accuracy, surface finish, consistent trial samples, technical support, and delivery to schedule.
No. The product details list trial testing and inspection, but do not clearly include final customer approval within the quoted period. Ask the supplier to state the end milestone in writing.
A schedule that says mass production begins 7–15 days after sample approval treats approval as a separate step. Likewise, ask whether “sample confirmation” means the supplier’s internal check or your formal sign-off.
Request dates or durations for mould completion, T1 trial, dimensional inspection, sample submission, customer approval, any revision rounds, final inspection, and shipment. The schedule should also explain which events may extend the delivery date.
Do not judge a mould schedule by the number of days alone: establish what “delivery” means for your order. For the listed 20–35-day timeframe, confirm whether it covers mould manufacture and inspection only, or also includes T1 trials, revisions, final approval, and shipment. Longterm Mold supports OEM custom tooling, mould making with injection moulding, precision double-shot and overmoulding projects, and mould development followed by mass production. For technical guidance or project support, contact rogerluo@longterm-mold.com.
Longterm Manufacturing Solutions Limited, operating as Longterm Mold, was established in 2010. The company provides mould design, tooling, precision machining, mould manufacturing, and parts production for customers worldwide. It produces approximately 180 moulds each year and more than 120,000 precision-machined components, serving markets primarily in North America, Europe, and Australia. Its engineering and production teams work with small- and medium-batch orders and coordinate tooling trials, inspection, and production needs.
The company is ISO 9001:2015 certified and has project experience in consumer electronics, home appliances, and industrial plastic components.