Final payment for a high voltage power transformer should be released only after the buyer has completed a documented review of the factory acceptance test (FAT) package and the agreed pre-shipment inspection records. This checkpoint helps verify that the transformer tested at the factory is the same unit specified in the purchase order and approved technical drawings.
The most important inspection point before paying the balance is confirmation that all contract-required factory tests and final inspections have been completed successfully. The buyer should receive and review FAT documentation, routine test reports, applicable type test evidence, and records showing that the transformer passed full inspection before shipment.
For a 110 kV oil-immersed transformer, the documentation should be cross-checked against the approved drawing revision, nameplate information, technical specification, and purchase order. Any difference in ratings, accessories, connection arrangement, standards, or physical configuration should be clarified and resolved before the final payment is authorized.
Factory acceptance testing provides evidence that the supplied transformer has undergone the required manufacturing and performance checks. Buyers should confirm that the test reports identify the actual transformer being delivered, including serial number or other traceable unit information.
The product information for the listed transformer includes FAT, routine testing, type testing, and complete pre-shipment inspection. Routine test results should be reviewed as part of the delivery acceptance file, while type test documentation should be checked according to the contractual and technical requirements for the project.
The listed product is part of a low-loss oil-immersed transformer range covering 110 kV, 115 kV, and 123 kV applications. Its stated nominal characteristics include a rated voltage of 110 kV, a frequency of 50/60 Hz, and a rated capacity of 1,800 kVA. These figures are reference product data and must be matched with the configuration actually ordered.
Before releasing payment, compare the approved technical drawings and order documents with the nameplate data and FAT records. Check the voltage level, capacity, frequency, cooling arrangement, tap changer details, terminals, protection accessories, and any project-specific requirements stated in the contract.
Full inspection before dispatch should be treated as a mandatory payment condition when it is included in the supply agreement. This review should confirm that the transformer is complete, correctly identified, properly prepared for transport, and accompanied by the required quality and test records.
It is also advisable to establish the acceptance process before production testing begins. The contract should define which reports are required, which drawing revision controls acceptance, whether deviations require written approval, and who has authority to sign off on the inspection results.
Grid infrastructure and industrial power projects may require the purchaser, consultant, or an independent inspector to witness key factory tests. The company business information indicates that witness inspection and third-party inspection can be arranged. However, the exact scope, notification period, attendance requirements, and report format should be agreed in the order rather than assumed.
Company-level information also refers to ISO 9001 quality management, factory testing, and IEC and GB compliance. These statements should be evaluated separately from the individual product listing, which identifies IEEE and IEC standards. The applicable standards for acceptance should always be those written into the purchase contract and approved technical documentation.
| Checkpoint | Buyer verification | Listed product information |
|---|---|---|
| Factory acceptance test | Confirm FAT records are complete and traceable to the transformer being shipped. | FAT is identified for the product. |
| Routine and type tests | Review agreed test reports and verify compliance with approved requirements. | Routine tests and type tests are listed. |
| Final pre-shipment inspection | Verify that the full inspection is complete and all required records have been issued. | Full inspection before shipment is listed. |
| Technical configuration | Compare ratings, standards, drawings, and accessories with the order. | IEEE and IEC; 110 kV, 50/60 Hz, 1,800 kVA. |
| Witness inspection | Confirm whether buyer or third-party attendance is contractually required. | Witness and third-party inspection are available in company business information. |
Reported project references include a 110 kV transformer application for an industrial park in Vietnam and a 25 MVA grid renovation project in Madagascar. Such cases may demonstrate application experience, but they are not a substitute for the FAT and inspection evidence required for a new transformer order.
The listed delivery period is 45–60 working days after receipt of the deposit and confirmation of technical drawings. Product support information includes a 72-hour global technical response, site commissioning and training, spare parts, and remote diagnostics. These services can support project delivery, but final payment terms should remain tied to the inspection and acceptance conditions agreed in the contract.
The buyer should review FAT reports, routine and type test records where applicable, and completed pre-shipment inspection documentation. All records should correspond with the approved drawings and the ordered transformer configuration.
The listed transformer data states 110 kV rated voltage, 50/60 Hz frequency, and 1,800 kVA capacity. Confirm that these and all other nameplate values match the project-specific order.
Witness and third-party inspection are referenced in the company business information. Buyers should define the inspection scope, schedule, responsible parties, and required documentation before factory testing takes place.
The final payment milestone for a high voltage power transformer should be based on documented acceptance, not simply on production completion or shipment readiness. Review the FAT package, verify routine and type test evidence as required, confirm completion of the pre-shipment inspection, and match every record to the approved drawings and purchase order. Any discrepancy should be closed before the balance is released.
For technical solutions or support, contact support@vziman.com.
Zhejiang Vziman Electric Power Technology Co., Ltd. is the parent company of Zhejiang Vziman Electric Group Co., Ltd., whose related firms originate from Zhejiang Powertech Electric Co., Ltd. The group focuses on the research, manufacture, and service of power electrical equipment, including transformers, switchgear, distribution systems, power automation solutions, and engineering services. Its markets cover more than 100 countries and include utility, industrial, grid, and renewable-energy projects. The company profile lists UDEM certification for substations, transformers, and switchgear, as well as CNAS accreditation for testing of a specified oil-immersed transformer model.