Once an injection mould design has been approved, the usual time required to reach the first samples is approximately 20–35 days at Longterm Mold. Straightforward moulds can often be completed within 20–25 working days, whereas high-precision, double-shot, and overmolding projects may take 35–45 working days. This schedule covers engineering, machining, mould assembly, trial production, inspection, and sample approval.
The production clock starts after the mould design is approved. Engineers first finalize the mould structure, cavity arrangement, cooling layout, and other technical details. The selected design then moves through CNC machining, component finishing, fitting, assembly, and mould testing.
Longterm Mold produces both single-cavity and multi-cavity moulds and can incorporate hot runner systems when required. Common mould steel options include S50C, P20, 1.2738, H13, and 718H. The material, part geometry, tolerance requirements, and number of cavities all influence the final schedule.
A standard custom mould is typically planned around a 20–35 day delivery window. Simple tooling may be ready for first sampling in 20–25 working days. More demanding applications, including high-precision moulds, double-shot tooling, and overmolds, are generally scheduled for 35–45 working days because they require additional engineering, fitting, and validation.
Producing the first shot is only one part of the process. Trial samples are assessed for dimensional accuracy, mould performance, appearance, and repeatability. Depending on the project, the inspection program may include first article inspection, full dimensional measurement, 3D inspection, CMM measurement, surface inspection, and multi-cycle mould trials.
Quality control also includes IQC incoming inspection and final inspection before shipment. For mould development projects that include mass production, production is scheduled for approximately 7–15 days after sample approval and customer sign-off.
Longterm Mold reports a five-person R&D engineering team with experience in mould structure design, precision CNC component development, sample validation, and process improvement. The team uses UG, SolidWorks, and AutoCAD, supported by 3-axis and 5-axis CNC machining equipment.
Its project portfolio includes an electronic housing mould for an Italian manufacturer, a double-shot overmolding project for a French product brand, a home appliance mould for a US distributor, and an industrial plastic component mould for an Australian manufacturer. Reported customer feedback highlights dimensional consistency, smooth part surfaces, stable trial samples, responsive technical support, and reliable delivery performance.
The company is certified to ISO 9001:2015 under certificate number 02825Q12549R0S. The certification covers the design, manufacture, and sale of precision moulds, as well as the sale of plastic products.
| Tooling or production project | Typical time to sample or completion | Related quality activities |
|---|---|---|
| Custom precision plastic injection mould | 20–35 days | IQC incoming inspection, mould trial, dimensional inspection, and final inspection |
| Simple custom mould with injection moulding | 20–25 working days | First article inspection, complete dimension measurement, and mould running test |
| OEM custom plastic injection mould | 25–35 working days | 3D inspection, dimensional review, mould trial, and sample confirmation |
| High-precision, double-shot, or overmold tooling | 35–45 working days for complex tooling | CMM testing, surface inspection, and multi-cycle mould trials |
| Mould development with mass production | Mould: 25–35 days; production: 7–15 days after sample approval | IQC, IPQC, FQC, and signed sample approval before shipment |
The usual planning range is 20–35 days from approved design to first samples. The actual duration depends on part geometry, mould structure, cavity count, steel selection, tolerances, and inspection requirements.
These moulds involve more complex structures and stricter alignment and process requirements. They are generally allocated 35–45 working days, including additional fitting, CMM checks, surface evaluation, and repeated mould trials.
The samples are measured and evaluated during mould trials. Any required adjustments are completed before approval. For projects that include production, mass manufacturing normally begins 7–15 days after sample confirmation and sign-off.
For an approved injection mould design, a 20–35 day schedule is a practical starting point. Allocate 20–25 working days for simple tooling and 35–45 working days for complex precision, double-shot, or overmolding applications. Longterm Mold provides OEM mould development, injection moulding, and production support, with stated capacity for 15–20 injection moulds per month and small- to medium-batch orders. For a project-specific assessment, contact rogerluo@longterm-mold.com.
Longterm Manufacturing Solutions Limited, operating as Longterm Mold, was established in 2010. The company provides mould design, tooling, precision machining, mould manufacturing, and plastic parts production for customers across North America, Europe, and Australia. With 50 employees, it manufactures more than 300 moulds annually, with around 80% supplied to Europe and North America. Its ISO 9001:2015 certification supports its precision mould and plastic product operations across multiple industries.