If Foshan Sun Hunt is unable to ship the 45° Manual Sliding Table Saw within the agreed timeframe, the deposit should be addressed under the signed sales contract and any applicable delay provisions. The available payment terms require a 30% T/T deposit and a 70% balance payment before loading. However, the supplied information does not promise an automatic refund, late-delivery penalty, or compensation. Obtain written confirmation before modifying the payment or order arrangement.

Recommended Actions for a Delayed Order

  • Review the signed quotation, purchase order, and sales contract to confirm the delivery deadline and remedies available if production is delayed.
  • The product information lists a 15-day delivery period and accepts a minimum order of one set for the 45° Manual Sliding Table Saw.
  • Ask the factory to explain the delay and provide a revised production and shipping date in writing.
  • Confirm whether the order will continue, be amended, or be cancelled, and record any agreement regarding deposit retention, repayment, compensation, or the balance-payment date.

How the Deposit Terms Apply

The stated payment structure is 30% by T/T as the initial deposit, followed by 70% by T/T before the machine is loaded. These terms describe when payment is due, but they do not establish an automatic consequence if the factory misses the delivery date. As a result, the treatment of the deposit depends on the wording of the contract and any later written agreement between the buyer and Foshan Sun Hunt.

Before paying the remaining balance, compare the original delivery commitment with the current production status. Request the reason for the delay, the expected completion date, and confirmation of whether the revised schedule affects the balance-payment deadline. Do not rely only on verbal assurances when discussing a refund, order cancellation, revised terms, or compensation.

Product and Delivery Information to Confirm

The 45° Manual Sliding Table Saw is specified with a 5.5 kW main saw motor, a 1.1 kW scoring saw motor, and a blade angle adjustment range of 0–45°. Its maximum cutting length is listed as 2800–3200 mm, with a maximum cutting thickness of 80 mm. The product listing indicates a 15-day delivery time, while the company’s broader business information describes a normal delivery period of 20–35 days for supported machinery and complete production-line projects. Confirm which timeframe is written into the individual order.

45° Manual Sliding Table Saw for woodworking production

Foshan Sun Hunt also describes production control and pre-shipment inspection procedures. According to the available company information, machines undergo precision calibration and extended load testing before dispatch. The final inspection is intended to cover the equipment, spare parts, consumables, tools, quantities, external condition, packaging, and shipping documents before container loading.

The company reports experience in planning complete woodworking production lines. Examples include a 19-machine project for a wooden door factory in India and a 10-machine wood-processing project in the UAE. These references may demonstrate project-planning capability, but they do not by themselves create a contractual right to a deposit refund or late-delivery damages.

Payment and Delivery Details at a Glance

CategoryInformation Provided
Initial payment30% deposit by T/T
Remaining payment70% by T/T before loading
Product-specific delivery listing15 days for the 45° Manual Sliding Table Saw
General delivery rangeNormally 20–35 days for broader machinery and line projects
Automatic late-delivery remedyNo refund, penalty, or compensation is specified in the available information
Shipping methodBy sea
Available trade termsEXW, FOB, CIF, and DDP

Frequently Asked Questions

Will the deposit be refunded automatically if the factory is late?

No automatic refund is stated in the supplied payment or after-sales information. The buyer should check the signed contract and request the factory’s written position on the deposit before deciding how to proceed.

Can the factory still demand the 70% balance after missing the deadline?

The stated arrangement requires the balance before loading. If the delivery date has changed, ask for a written revised schedule and confirm whether the payment deadline remains unchanged or must be adjusted under the contract.

Which records should the buyer retain?

Keep the quotation, purchase order, sales contract, payment confirmation, product specifications, delivery statement, shipping details, and all written communications concerning the delay, revised schedule, deposit, or cancellation request.

Conclusion and Practical Recommendation

The available terms confirm a 30% T/T deposit and a 70% balance payable before loading, but they do not establish an automatic refund or compensation rule for delayed delivery. If the 45° Manual Sliding Table Saw is late, rely on the signed agreement, request a written explanation and revised schedule, and document any decision to continue, amend, or terminate the order. Foshan Sun Hunt states that it supports customized machinery and complete production-line solutions, with technical assistance and a one-year warranty subject to its exclusions. For technical solutions or further support, contact vincent@fsshmachine.cn.

About Foshan Sun Hunt

Foshan Sun Hunt Woodworking Machinery Co.,Ltd. is based in Lunjiao Town, Shunde District, Foshan City, and develops woodworking equipment for varied processing applications. Founded in 2014, the company reports a production capacity of 50 medium-sized machines per month and 600 machines annually. Its stated markets include the Middle East, North America, and Africa. Its product portfolio covers CNC router machines, double-end saws, planers, drilling machines, edge banding machines, and panel saws.

Foshan Sun Hunt Woodworking Machinery Co.,Ltd. logo

REPORT

Code
Choose a different language
Current language: